Maintenance and release schedule
================================

You can find the detailed schedule for major and maintenance releases at: `detailed schedule <https://github.com/nextcloud/server/wiki/Maintenance-and-Release-Schedule>`_.

Major releases
--------------

Major releases are typically scheduled once every 4 months with the first 10 weeks being the development phase followed by freeze phase with four beta release, two RCs and one final each one with an interval of 1 week. Specific dates for each release can be found on `detailed schedule <https://github.com/nextcloud/server/wiki/Maintenance-and-Release-Schedule>`_.

Major releases are planned to be actively maintained for 12 months after their initial release. For long term support options check out the `Nextcloud Subscription <https://nextcloud.com/enterprise/>`_ offered by `Nextcloud GmbH <https://nextcloud.com>`_.

Maintenance releases
--------------------

Maintenance releases are scheduled in a 4 week cycle with one week before the release date having the freeze and RC 1.